Valley Park – V36
Newtownards
The work consists of Electrical Engineering services of a multi use games area, sand carpet pitches, synthetic play courts, play areas, fitness area, pond area, approach road, retaining walls and walking trails and paths.
The work consists of Electrical Engineering services of a multi use games area, sand carpet pitches, synthetic play courts, play areas, fitness area, pond area, approach road, retaining walls and walking trails and paths.
To Include
- NIE Intake Panel
- Mains Distribution
- Site Lighting
- 3G Pitch Floodlighting
- Site Sound & PA System
- Site CCTV System
- Amenity Lighting
- Flood Warning Systems
Client Newtownabbey Borough Council
Details Electrical Engineering services
Main Contrator Fox Contracts
M&E Consultant AH Design Consultants
Duration 56 Weeks